Application of fall-back procedures |
|
|
Regulation Article |
Article 7.2 of IN IF Article 3.11 of mFRR IF Article 3.10 of aFRR IF |
|
Regulation text |
|
|
Detailed description |
The following events shall be published: Disconnection and reconnection of
End date and time must always be provided. An estimate shall be provided |
|
Specification of calculation |
No calculations foreseen. |
|
Primary owner of the data |
|
|
Data provider |
IN, aFRR and mFRR platforms |
|
Aggregation |
|
|
Publication deadline for ENTSO-E |
No later than 30 minutes after the end of the first ISP of the disconnection and reconnection of the TSO. |
|
Updates |
Changes to planned or actual date and time of disconnection/reconnection of TSO shall be submitted as updates to the originally published information. Changes to the planned or actual date and time of service suspension and reestablishment on European platform shall be submitted as updates to the originally published information. |
|
Comments |
The detailed description outlined above allows data consumers to distinguish “temporary incidents linked to the complexity of the real-time processes and the limitations of the IT systems, with an expected duration longer than 5 minutes and shorter than 30 minutes” as foreseen by aFRR IF art. 3.10. |