| Installed capacity by Production Unit | ||
| Regulation Article | TR articles 14.1.b and 14.2.b | |
| Regulation text | Information about production units (existing and planned) with an installed generation capacity equaling to or exceeding 100 MW. The information shall contain:
The information shall be published annually for the three following years no later than one week before the beginning of the first year to which the data relates. | |
| Detailed description | Information about production units (existing and planned) with an installed generation capacity equaling to or exceeding 100 MW. The information shall contain:
Note: The definitions of the commissioning and decommissioning date are out of scope for TSOs and, in order to ensure qualitative data publications, it shall be drafted by NRAs in coordination with primary owners of the data taking into account the ongoing discussions. The information shall be published annually for the three following years no later than one week before the beginning of the first year to which the data refers. Information should refer to January 1st of each year for the 3 following years. | |
| Specification of calculation | Information should refer to the 1st January of each year for the 3 following years | |
| Primary owner of the data | Owners of production units for nominated plants. | |
| Data provider | TSOs or other Data Provider of information depending on local organization. | |
| Aggregation | No aggregation necessary | |
| Publication deadline for ENTSO-E | One week before the first year to which the data refers | |
| Update | Usually no update | |
Comments
0 comments
Article is closed for comments.