Physical Flows |
|
|
Regulation Article |
TR article 12.1.g |
|
Regulation text |
Physical flows between bidding zones per market time unit. The information shall be published for each market time unit as closely as possible to real time but no later than one hour after the operational period |
|
Detailed description |
Physical flows between bidding zones per market time unit as closely as possible to real time and at the latest H+1 after the end of the application period. |
|
Specification of calculation |
Average netted values (in MW). Values are netted over the period of measurement. |
|
Primary owner of the data |
TSO or group of TSOs |
|
Data provider |
TSO or group of TSOs |
|
Aggregation |
According to the actual cross zonal capacity calculation and allocation procedures, the data required under TR articles 11 and 12 may also be provided and published in nonaggregated form (i.e. on particular borders between TSOs), in case TSOs belong to different Member states. |
|
Publication deadline for ENTSO-E |
at the latest H+1 after the end of the operating period |
|
Updates |
Yes |