Monthly forecasted cross-zonal capacity |
|
Regulation Article |
TR article 11.2 (Publication of info as set out in Annex) |
Regulation text |
|
Detailed description |
The forecasted NTC (MW) per direction between bidding zones, including technical profiles. |
Specification of calculation |
Submission of the data can be done with higher resolution (A higher resolution means that the submission could be done with a more accurate information, E.g. the data provider can send data with the daily resolution even if publication requirement is one value per week) Note: same rule of calculation applies to yearly, monthly, weekly and intermediary such as semestrial |
Primary owner of the data |
TSO or CCC |
Data provider |
TSO or CCC |
Aggregation |
According to the actual cross zonal capacity calculation and allocation procedures, the data required under TR articles 11 and 12 may also be provided and published in non-aggregated form (i.e. on particular borders between TSOs), in case TSOs belong to different Member states. |
Publication deadline for ENTSO-E |
2 working days before the gate closure of the monthly allocation process. |
Updates |
Yes |
Comments
0 comments
Article is closed for comments.