Day ahead offered cross-zonal capacity |
|
|
Regulation Article |
TR article 11.2 (Publication of info as set out in Annex) |
|
Regulation text |
|
|
Detailed description |
For NTC allocation method: the offered capacity (MW) per direction between bidding zones, including technical profiles. |
|
Specification of calculation |
|
|
Primary owner of the data |
TSO or CCC |
|
Data provider |
TSO or CCC |
|
Aggregation |
According to the actual cross zonal capacity calculation and allocation procedures, the data required under TR articles 11 and 12 may also be provided and published in non-aggregated form (i.e. on particular borders between TSOs), in case TSOs belong to different Member states. |
|
Publication deadline for ENTSO-E |
1 hour before spot market gate closure, for each market time unit |
|
Updates |
Yes in case of force majeure |
Comments